wisselstoring

Points failure: Utrecht-Rhenen (11 November 2018)

  1. Disruption resolved Last update

    Between Driebergen-Zeist and Rhenen the restrictions are resolved.

  2. Show complete timeline…
  3. Disruption reported

    Between Utrecht Centraal and Rhenen far fewer trains are running due to a points failure.
    The extra travel time may be up to 60 minutes.
    This will take until approximately 3:00 PM hours.

Location of this disruption

This disruption is between Driebergen-Zeist and Rhenen.

Map of the location of this disruption

See the disruptions map for a live overview of all disruptions in the Netherlands.

More about this disruption

Statistics

This disruption started at 1:02 PM on November 11, 2018 and took 1 hour, 22 minutes in total.

For statistics, this disruption is caused due to a points failure.

Affected lines

The following lines are affected by this disruption:

Operators

This disruption affects trains operated by NS.

Got delayed due to this disruption? You may be reimbursed.

Refunds and passenger rights